In mid-August 2021 we competed 3,124 SF of All-Stone permeable sidewalks in color Beach...
We paved a 293 SF All-Stone porous sidewalk in color Botticino Marble in late July 2021. We also performed many tree preservation tasks as well such as: SSAT root pruning, aerate/decompact soil, cambistat tree growth regulator, soil amendments, IPM inspections,...
In late June 2021 we completed a 1,438 SF Flexi-Pave courtyard area in color Olive Fog. We also installed a 699 SF Flexi-Pave overlay in color Evergreen on top of an existing concrete...
We completed a 570 SF pathway in color Chestnut in early June...
In late April 2021 we completed the picnic table and bike rack installation which included the following: Sawcut Existing asphalt Subbase preparation including excavation of gravel/permeable subbase, table and bike rack foundation, grading of swale 2 Nyloplast Basins...